Heavy/Highway
Reconstruction of Route 213 – D253884
Location: Rosendale, New YorkOwner: NYS Dept. of Transportation
Approx. Revenue: $2,461,000.
Contact: Frank Naccaratto, A.J. Bauman
(914) 431-5932
Description: Realignment & reconstruction of approx. 1,200 LF of State Rte. 213 and reconstruction & resurfacing of approx. 5 miles of County Road 123. Work includes the drilling & blasting of 30,000 CY of rock excavation & backfill, placement of approx. 15,000 tons of bituminous concrete items, placement of approx. 6,000 CY of subbase material, clearing & grubbing operations, work also included misc. pipe work approx. 600 LF, temporary traffic signal, misc. concrete work, guiderail work approx. 5,000 LF, striping items & highway signing.
Completion: November 1992
Beekman Street Bridge Over Metro North D253467
Location: Beacon, N.Y.Owner: NYS Dept. of Transportation
Approx. Revenue: $3,050,000.
Contact: Joe Osso, A.J. Bauman - (914) 431-5932
Description: Construction of a 300' three span curved composite girder bridge over 3 tracks of Metro North Railroad. Work consisted of approx. 3,700 LF of steel H piles, approx. 800 CY structural concrete, setting of 6 sets of structural steel girders total weight approx. 550,000 lbs. Installation of insulated water & sewer line under the bridge, forming & pouring approx. 11,000 SF concrete deck slab. Placement of approx. 1,200 CY of lightweight fill. Demolition of existing 210' 5 span steel structure. Incidental work included road work misc. pipe work, lighting fixtures, temporary steel sheet piling, guide rail & signing.
Completion: April 1992
Airport Access Road
Location: LHJ Airport Wawarsing, New YorkOwner: Town of Wawarsing, N.Y.
Approx. Revenue: $600,000
Contact: Joseph Stoeckler - (914) 647-6570
Description: Construction of 5,000 LF of new access roadway, work included excavation of approx. 21,000 CY of earth, placement of subbase material, placement approx. 3,600 tons asphalt incidental items included fencing, striping misc. pipe work, rip rap, guide rail & signing.
Completion: November 1991
Scour Protection at Various Bridges D254209
Location: Various Counties, N.Y. StateOwner: NYS Dept. of Transportation
Approx. Revenue: $230,000.
Contact: L. Stevens, J.E. Taylor - (518) 474-6562
Description: Excavation for & placement of approx. 2,200 CY of rip rap abutment protection along 9 bridges in NY State. Incidental work included cofferdams & turbidity curtain.
Completion: August 1991
Reconstruction of Wisner Avenue Bridge
Location: Wisner Avenue, Newburgh, N.Y.Owner: Orange County Dept. of Public Works
Approx. Revenue: $225,000.
Contact: Ron Meyers - (914) 294-7951
Description: Removal of existing 25' structural steel span & replacing with twin 10x10 pre-cast box culvert. Work includes placement of approx. 72' of pre-cast 10x10 box culvert. Incidental items of work included roadway, guiderail bridge railing and excavation
Completion: January 1991
Michael Road Bridge
Location: East Greenbush, New YorkOwner: Town of East Greenbush
Approx. Revenue: $21,000.00
Contact: Mr. Thomas DiGiullio - (518) 477-6103
Description: Removal of existing bridge and replacement with aluminum pipe arch. Work includes drilling & blasting of existing substructure, removal of existing bridge, excavation stream bank, construction of aluminum pipe arch, placement embankments roadways subbase, rack rip rap.
Completion: December 1990