Heavy/Highway

Route 209 Reconstruction

Attention: open in a new window. PDFPrintE-mail

Location: Wawarshing, New York
Owner: New York Department of Transportation
Approx. Revenue: $3,447,000.00
Contact: Donald Brott /A.J. Bauman - (914) 431-5950
Description: Reconstruction and realignment of approximately 1.1 miles along Route 209 in Wawarshing. Included in the realignment is removal and replacement of 120' structural steel bridge, new abutments and approximately 11,000 tons of asphalt work. Rip rap protection along Route 55, approximately 6,000 C.Y.
Completion: December 1990
   

Streambank Stabilization of Tsatsawassa Lake Road

Attention: open in a new window. PDFPrintE-mail

Location: Nassau, New York
Owner: U.S. Department of Agriculture
Approx. Revenue: $18,000.00
Contact: Mr. Jeffrey Wheaton - (518) 472-2728
Description: Stabilization of stream channel. Work includes channel clearing and shaping, excavation of slope and placement of rock rip rap, dewatering.
Completion: October 1990
   

Reconstruction of Derby Road Bridge over Conrail

Attention: open in a new window. PDFPrintE-mail

Location: Wallkill, New York
Owner: NYS Dept. of Transportation
Approx. Revenue: $ 750,000.00
Contact: Mr. Joseph O'Malley, Jr.-A.E. Dickson
(914) 431-5950
Description: Installation of 10,000 C.Y. of embankment for approaches. Removal of existing steel structure. Install approx. 5,000 S.F. of reinforced abutments and bridge deck. Paving approaches & related work.
Completion: December 1989
   

Safety Improvement Along NYS Thruway

Attention: open in a new window. PDFPrintE-mail

Location: Along the NYS Thruway in Ulster & Greene Counties
Owner: NYS Thruway Authority
Approx. Revenue: $ 789,000.00
Contact: Mr. Jim Miller - (518) 436-2905
Description: Excavation and cleaning of ditches and swales. Installation of culvert end sections, rip-rap and pipe at approx. 60 locations. Also included installation of guide rail items & concrete barriers and maintenance & protection of traffic.
Completion: December 1989
   

Rock Slope Stabilization Along Route 9W

Attention: open in a new window. PDFPrintE-mail

Location: Stoney Point, New York
Owner: NYS Dept. of Transportation
Approx. Revenue: $ 990,000.00
Contact: Mr. Harry Henck-A.E. Dickson
(914) 431-5950
Description: Removal of approx. 20,000 C.Y. of rock ledges with drilling and blasting along Route 9W in the Town of Stoney Point. Also included
miscellaneous work.
Completion: August 1989
   

Rock Remediation Along NYS Thruway

Attention: open in a new window. PDFPrintE-mail

Contract No. TAA 88-29
Location: Greene County
Owner: NYS Thruway Authority
Approx. Revenue: $ 4,400,000.00
Contact: Mr. James Miller-NYS Thruway
(518) 436-2905
Description: Removal of and disposal of approx. 95,000 tons of rock overhang along the NYS Thruway. Also included installation of guide rail and rock fall mesh.
Completion: November 1988
   