Flood Control/Beach Erosion
Confined Dredge Material Disposal Facility Construction & Operation*
Locations: Bayonne, Hudson County, New JerseyOwner: Bayonne Local Development Authority
Contact: Tim Rioux, LGA Eng (732)961-2162
Approx. Revenue: $4,365,247.00
Description: Construct and operate dredge material disposal facility for 1.3 million cubic yards of sand. Work includes outfall structure, spud barge and dredge piping, sand placement and erosion controls.
Completion: November 2007
Gilboa Dam Interim Stability Improvements*
Location: Gilboa, Schoharie County, New YorkOwner: Dept of Environmental Protection
Contact: Dino Kartofilis, Nicholson Constr (412) 221-4500 and Tom Robinson, DEP (845) 926-7159
Approx. Revenue: $3,500,000.00
Description: Project includes installation of multi-strand anchors, anchored into bedrock to stabilize existing dam. Responsible for providing access to the site, erosion control, water diversion cofferdams, installation of 500 ft by 40 ft high work platform for drill rigs, removal of loose debris and façade stone from the face of the dam and design/installation of 10,000 sy of debris fall protection netting on the face of the dam. The project also includes 740 cy of replacement concrete for a notch cut into the dam under a previous contract.
Completion: December 2006
Repair Construction & Rehabilitation of Little Dam Lake Dam*
Location: Sterling Forest State Park Preserve, Orange County, Town of TuxedoOwner: NYSOPR & HP, Palisades Interstate Park Commission
Contact: Larry Soeller, PIPC (845) 786-2701
Approx. Revenue: $1,098,000.00
Description: Remove and construct new concrete Ogee Spillway and Core Wall, rock excavation, cofferdams, dewatering, excavate & realign stream channel & rip rap, construct Earthen Dam, place rip rap protection stone, topsoil & seed.
Completion: September 2005
Beachfill, Absecon Inlet to Great Egg Harbor Inlet*
Location: Atlantic City & Ventnor City, New JerseyOwner: U.S. Army Corps of Engineers, Phil District
Contact: Sam Morrison, Great Lakes Dredge & Dock (630) 574-3000
Approx. Revenue: $7,100,000.00
Description: Removal & installation of 4,475 lf of stormwater outfall pipes on timber pile supports. Construction of 15 wood handicap dune crossovers and 13 select fill vehicular crossovers. Also includes installation of 100 modular pedestrian dune crosswalks.
Completion: March 2005
Townsends Inlet to Hereford Inlet Shore Protection*
Location: Avalon and Stone Harbor, New JerseyOwner: Army Corps of Engineers, Subcontractor to Great lakes Dredge & Dock
Contact: Sam Morrison - (630) 574-3000
Approx. Revenue: $1,545,000.00
Description: Work includes construction of pedestrian, handicapped and vehicular select fill dune crossovers and five pedestrian handicapped wood crossovers on the beaches in Avalon and Stone Harbor, NJ.
Completion: June 2003
Beach Renourishment at Sea Bright and Monmouth Beach*
Location: Spring Lake and Asbury Park, New JerseyOwner: Army Corps of Engineers-NATCO
Contact: Russell Zimmerman - (630) 574-3000
Approx. Revenue: $1,500,000.00
Description: Work includes the notching of two groins along the New Jersey Coastline in the towns of Spring Lake and Asbury Park, NJ. Work includes disassembling the existing groin (jetty) and re-excavating the center portion of the notch along surf zone. Lower it approximately 15 feet and then place new bedding stone and reset the existing armor stones. Work also includes disposing of excess material, dewatering and misc. related work.
Completion: April 2003
North Ellenville Repair & Restoration
DACW-51-95-C0056Location: Rondout Creek, Ellenville, N.Y.
Owner: U.S. Army Corps of Engineers
Approx. Revenue: $1,850,000.
Description: Repairs to Rondout Creek including excavation and installation of 50,000+ tons rip rap and grout bags along stream bottom and slopes.
Completion: January 1997
Scour Repair at 16 Bridges D254155
Location: Delaware, Otsego, Schoharie CountiesOwner: NYS Dept. Of Transportation
Approx. Revenue: $421,000.
Contact: Stan Fuller, EIC, NYSDOT
(607) 432-5810
Description: Scour repair at 16 bridges in various counties & the construction of a concrete & gabion outfall structure. Work includes clearing & grubbing, approx. 4,000 CY of unclassified excavation, grading & reshaping of approx. 2,000 LF of channel, construction of 30 cofferdams, placement of approx. 2,500 CY of stone fill rip rap, installation of approx. 260 CY of gabions & 80 CY of concrete for outfall structure seeding & erosion control measures.
Owner: City of Saratoga Springs, New York
Approx. Revenue: $155,000.
Completion: November 1992
Scour Protection at Various Bridges D254209
Location: Various Counties, N.Y. StateOwner: NYS Dept. of Transportation
Approx. Revenue: $230,000.
Contact: L. Stevens, J.E. Taylor - (518) 474-6562
Description: Excavation for & placement of approx. 2,200 CY of rip rap abutment protection along 9 bridges in NY State. Incidental work included cofferdams & turbidity curtain.
Completion: August 1991
Michael Road Bridge
Location: East Greenbush, New YorkOwner: Town of East Greenbush
Approx. Revenue: $21,000.00
Contact: Mr. Thomas DiGiullio - (518) 477-6103
Description: Removal of existing bridge and replacement with aluminum pipe arch. Work includes drilling & blasting of existing substructure, removal of existing bridge, excavation stream bank, construction of aluminum pipe arch, placement embankments roadways subbase, rack rip rap.
Completion: December 1990
More Articles...
- Streambank Stabilization of Tsatsawassa Lake Road
- Dike Construction at Reding Road
- Repair of Lower Reservoir Rip Rap Slope Protection Gilboa Dam
- Water Control Structure on Basherkill Marsh
- Dam Modification for Camp Harriman
- Excavate Stream Channel
- Emergency Shore Stabilization Berth 1 & 2
- Rondout Creek Improvements
- Protective Seawall-Liberty State Park
Page 1 of 2