Landfill

Town of Sand Lake Landfill Closure

Attention: open in a new window. PDFPrintE-mail

Location: Sand Lake, New York
Owner: Town of Sand Lake, N.Y.
Approx. Revenue: $928,000.
Contact: Peter Sutherland
Smith & Mahoney - (518) 463-4107
Description: Work included the closure of 16+ acres of municipal landfill.
Completion: August 1994
   

Town of Coeymanns Landfill Closure

Attention: open in a new window. PDFPrintE-mail

Location: Coeymanns, New York
Owner: Town of Coeymanns, New York
Approx. Revenue: $1,804,000.
Contact: Rick Lowenstein
Clough Harbor Assoc. - (518) 453-4500 Description: Work included a complete closure of an 18+ acre municipal landfill including grading of waste, liner system and cover material.
Completion: November 1993
   

Town of Wilton Landfill Closure Project – Contract No. 1

Attention: open in a new window. PDFPrintE-mail

Location: Wilton, N.Y.
Owner: Town of Wilton
Approx. Revenue: $639,150.
Contact: Chris LaPlank, Clough Harbour & Assoc. (518) 453-2882
Description: Closure of 7 acre municipal landfills. Work included site grading of existing work, placement of approx. 67,880 SY of geotextile, 8,500 CY of gas vent material, place 15,000 CY clay cap, install gas vents, monitor wells, HDPE geomembrane liner & Q.C. testing.
Completion: December 1992
   

Orange County Sanitary Landfill – Phase 2B*

Attention: open in a new window. PDFPrintE-mail

Location: Goshen, N.Y.
Owner: Orange County PDW
Approx. Revenue: $10,700,000.
Contact: Tim Leonard
Wehran Engineer - (914) 343-0660
Description: Construction of 20 acre solid waste landfill cell. Work included excavation and disposal of approx. 125,000 CY of earth. Also includes placing of and compaction of approx. 300,000 CY of imported fill material. Included mining, hauling and placement of approx. 140,000 CY of clay material. Placement of approx. 90,000 CY of drainage sand material. Installation of approx. 1.7 million square feet of 60 mil HDPE liner. Installation of leachate collection system which included approx. 7,000 LF of collection pipe, approx. 2,000 LF of dual HDPE containment pipe with monitoring riser and cleanout and 12 - 6' diameter manholes. Also included are topsoil and seeding of approx. 27 acres.
Completion: May 1992
   

Preliminary Site Work Phase IIA Orange County Sanitary Landfill

Attention: open in a new window. PDFPrintE-mail

Location: Goshen, New York
Owner: Orange County
Approx. Revenue: $2,584,000.00
Contact: Mr. Tim Leonard, Wehran Engineering
(914) 343-0660
Description: Initial site work for landfill. Work includes cleaning and grubbing of 21 acres, stripping of topsoil, demucking and placement of 220,000 C.Y. of embankment for landfill foundation
Completion: March 1991
   

Page 4 of 4