Utilities

Lake Sebago Water Distribution System

Attention: open in a new window. PDFPrintE-mail

Location: Bear Mountain, Rockland County, NY
Owner: Palisades Interstate Park Commission
Contact: Larry Soeller, PE (845) 786-2701 Ext 227
Approx. Revenue: $1,013,000.00
Description: Construction of 11,900 Linear feet of 6" and 4" HDPE Waterline system, including valves, water services, air relief valve and pressure reducing manholes to provide water to the Beach Pavilion and Camps at Lake Sebago in Harriman State Park. A key element of the project was the construction of an 800 Linear feet water line across Lake Sebago. The project was brought to completion in approximately one half the time period allowed for in the contract.
Completion: May 2007
   

Buffalo Diverse (Williams) Project*

Attention: open in a new window. PDFPrintE-mail

Location: Town of Buffalo, New York
Contract No.: 99P1722.04
Owner: Williams Communications
Approx. Revenue: $4,650,000.00
Description: Installation of approximately 6 miles of fiber optic cable. Work includes the installation of conduits, handholes and manholes, maintenance and removal of all traffic control requirements, all trenches and excavation, joining of conduit, shoring, backfilling, and restoration of the affected right-of-way.
Completion: March 2001
   

Site Water Distribution Upgrade

Attention: open in a new window. PDFPrintE-mail

Location: Rockland Psychiatric Center, Orangeburg, New York
Owner: Facilities Development Corp.
Approx. Revenue: $88,500.
Contact: Chystyna Gruca - (914) 365-2418
Description: Installation of piping system for power plant including pressure reducing valves, telemetry system, gate valves & miscellaneous appurtenance.
Completion: July 1992
   

Middletown Filter Plant Sewer Line

Attention: open in a new window. PDFPrintE-mail

Contract No. 86222.3
Location: Along City Road 78, Middletown, NY
Owner: Township of Middletown, NY
Approx. Revenue: $ 430,000.00
Contact: Mr Gary Chumard-Chumard & McEvilly
(914) 343-5016
Description: Installation of approx. 3,000 L.F. of various size polyvinyl chloride pipe & ductile iron pipe and related items
Completion: November 1988
   

Installation of Force Main

Attention: open in a new window. PDFPrintE-mail

Contract No. C36-1306-01-1
Location: Mid Orange Correctional Facility, Warwick, NY
Owner: Town of Warwick, NY
Approx. Revenue: $650,000.00
Contact: Mr. Anthony Cosenza-Hudson Engineering
(914) 986-9666
Description: Installation of 5,000 L.F. of 8" polyethylene pipe through swamp and approx. 9,700 L.F. of 12" ductile iron pipe through streets. Project included clearing of swanom temporary road construction and removal through swamp with eight stream crossings.
Completion: May 1987
   

Proposed Storm Sewer Improvement - McCall Place/Highland Terrace

Attention: open in a new window. PDFPrintE-mail

Contract No. 8456
Location: McCall Place/Highland Terrace area, Newburgh, NY
Owner: Town of Newburgh, NY
Approx. Revenue: $ 200,000.00
Contact: Mr. Gary Chumard-Chumard & McEvilly
(914) 343-5016
Description: Installation of 1,200 L.F. of various large sizes of reinforced concrete pipes and poured approximately 100 C.Y. of concrete headwalls to relieve flooding upstream.
Completion: December 1986